(Media Office)

In continuation of the work efforts to restore the Al-Dahra field to its previous era, the Drilling and Well Maintenance Section has worked during the past few days on the initial procedures for maintaining the basic valves for the wellheads, on closing and opening these valves, as well as the pressure valves tests. Then working on cleaning, lubricating and painting those wells to ensure the readiness of these wells for the return of production.

The work started in the middle of last July in the PL5 zone, which has a difficult nature, and the number of wells has so far reached more than 45 wells, and work is still going on in this zone.